CMSD - John Marshall High School


John Marshall High School is a new facility for the Cleveland Metropolitan School District that will replace the original high school on Cleveland’s near west side. The design of the new facility pays homage to the original 1932 building, providing a neo-classic, three-story academic wing fronting on West 140th Street.
  • Owner: Cleveland Metropolitan School District
  • Co-Owner: Ohio Facilities Construction Commission
  • Owners Agent: OHGR (Ozanne, Hammond, Gilbane & Regency)
  • Architect: TDA Architecture, part of the Cleveland Architectural Design Alliance (CEDA)
  • CM at Risk: ICON, LLC.
  • Location: 3952 W 140th St, Cleveland, OH 44111
  • Size: 207,000 square feet
  • Value: $ 40 million
  • Anticipated Bid Date: Early May, 2013
  • Construction: June 2013 through February 2015

PREQUALIFICATION OF SUBCONTRACTORS
ICON, LLC will be prequalifying subcontractors with criteria that has been pre-approved by the OFCC and the CMSD in accordance with the guidelines set forth by the State of Ohio for CMaR contracting. More information and documents related to this project delivery format can be found at http://ofcc.ohio.gov/Documents.aspx. Although ICON, LLC will share information on bids received with the Co-Owners, this is not a public bid opening. More information on bid delivery will be issued with the bid packages to pre-qualified subcontractors. Questions on the process should be sent to JMbidquestions@iconohio.com.

Contractors wishing to be considered for pre-qualification must do so by providing information on the web-tool at the link below. Information will be treated as confidential, and only shared with the members of ICON, CMSD, OFCC, and OHGR involved with the pre-qualification process.






Project Site Webcam

SUBCONTRACTOR BID PACKAGES
ICON will be receiving bids from prequalified subcontractors on the bid packages listed below. It is also ICON’s intent to allow for the bidding of Combination Bids. We believe that this practice will allow for additional competition in the market, sustain the viability of local general contractors, allow the inclusion of smaller subcontractors who might otherwise be ineligible, and provide the best opportunities for the success of CMSD’s Community Inclusion and Graduate Workforce programs. Scope indicated below are for general information, only. Detailed scopes of work will be issued with each bid package.

2A - Excavation – Preliminary Estimate $816,485

• General site grading
• Erosion Control
• Stone pavement base
• Construction fencing
• Site Utilities - sanitary, storm, dom. water & gas
• Temporary staging and construction entrance
• Misc. Demolition & Removals
• Snow removal

3A - Cast in Place Concrete – Preliminary Estimate $1,517,554

• Excavation for foundations w backfill
• CIP Concrete - building foundations, piers, etc.
• CIP Concrete - slab on grade
• Stone base & vapor barrier at SOG
• Insulation at slab/foundation
• Cast in Place Concrete - slab on deck
• CIP Concrete- curbs and walks
• Equipment pads
• Stair pan fill
• CIP Concrete - heavy duty concrete paving
• Draintile
• Joint sealants associated with above

4A – Masonry – Preliminary Estimate $5,408,208

• Masonry foundations
• Concrete masonry units
• Brick Veneer
• Cast stone
• Ground face block
• Installation of salvaged items
• Masonry reinforcing and grouting
• Masonry accessories, flashings, moisture barriers
• Receive, set, prime, & grout HM frames in masonry walls
• Receive & set loose lintels, bearing plates, imbeds
• Insulation at masonry walls
• Precast lintels F&I
• Masonry locker bases
• Joint sealants associated with above
• Waterproofing/vapor barriers associated with masonry
• Mock-ups & sample panels

5A – Metals – Preliminary Estimate $2,573,104

• Structural steel
• Base plates and anchor bolts
• Open web steel joists
• Floor and roof deck
• Miscellaneous metals
• Loose lintels
• Roof frames
• Roof drain pans
• Steel stairs & railings
• Toilet partition supports
• Deck edge
• Safety cables & toe protection
• Access ladders

6A - Carpentry & Specialties – Preliminary Estimate $2,835,560

• Interior and Exterior Rough Carpentry
• Hollow metal door & borrow light frames
• Door hardware
• Wood and hollow metal doors
• Overhead coiling doors
• Fire doors and shutters
• Walk-off mats
• Wall and corner guards
• Finish carpentry and trim
• Visual display boards
• Signage and directories
• Toilet partitions, screens & accessories
• Cubicle curtains and track
• Wire mesh partitions
• Metal storage shelving
• Display cases
• Residential appliances
• Fire extinguishers & cabinets
• Miscellaneous educational equipment
• Projection screens
• Window treatments
• Athletic equipment
• Telescoping bleachers

7A - Roofing and Metal Siding – Preliminary Estimate $1,579,366

• Low-sloped roofing system
• Protection board
• Insulation
• Flashing, counter-flashings & cant
• Wood blocking associated with roofing
• Architectural sheet metal
• Metal copings
• Scuppers
• Prefinished metal siding
• Roof hatches
• Joint sealants associated with above
• Prefinished aluminum louver

8A - Glass & Glazing – Preliminary Estimate $1,690,953

• Curtainwall systems
• Storefront
• Aluminum Entrances
• Associated hardware
• FRP entry doors
• Automatic door openers
• Spandrel panels
• Interior glazing
• Non-framed mirrors

9A – Interiors – Preliminary Estimate $2,482,135

• Light gauge metal framing - interior and exterior
• Gypsum board assemblies
• Acoustic & DW ceilings
• Access doors
• Resilient flooring
• Quarry & Ceramic Tile
• Athletic wood flooring
• Stage Wood Flooring
• Carpet
• Acoustic panels and treatments
• Painting
• FRP Panels

10B – Lockers – Preliminary Estimate $394,074

• Student lockers
• Athletic lockers
• Staff lockers
• Locker benches
• Fillers, sloped tops, etc

11A - Food Service Equipment – Preliminary Estimate $541,804

• Food service equipment
• Serving lines
• Dishwashers
• Hood w/ fire suppression
• Coolers & freezers

11B - Theater & Stage Equipment – Preliminary Estimate $19,800

• Curtains and Rigging

12A – Casework – Preliminary Estimate $1,312,680

• Educational casework
• Art-room casework
• Associated sinks, faucets
• Music room casework
• Instrument storage lockers
• Life Skills casework
• Media Center casework
• Science lab casework
• Fume hoods
• Resin tops & sinks

12B Loose Furnishings, FF&E – Preliminary Estimate $1,411,336

• Educational furnishings
• Media center furnishings
• Office / administration furnishings

14A – Elevators – Preliminary Estimate $100,485

• 3-stop elevator

21A - Fire Suppression – Preliminary Estimate $727,931

• Automatic sprinkler system
• Fire pump / jockey pump
• Balance and testing
• Hook-up range hood system
• Stand pipes

22A – Plumbing – Preliminary Estimate $2,842,609

• Water service entry / meter
• Backflow preventers
• Core Drilling
• Hot/cold water service
• Pipe insulation
• Plumbing fixtures
• Mop sinks
• Shower units
• Grease traps
• Rough-in and connection of food service equipment
• Rough-in and connection to science equipment
• Sanitary Waste & Vent Systems
• Acid waste system
• Compressed Air Systems
• Storm water system
• Natural gas system
• Gas Service and Meter
• System Testing

23A - HVAC & Integrated Automation – Preliminary Estimate $6,885,677

• Temporary heating requirements
• Heating Equipment & Distribution
• Cooling Equipment & Distribution
• Air Handling Equipment & Distribution
• Exhaust system
• Associated fire dampers, fire safing
• Heat recovery
• Temperature Control System
• Integrated building automation system

26A – Electrical – Preliminary Estimate $3,655,431

• Temporary electric requirements
• Electric site utilities
• Service & switchboards
• Grounding
• Branch panels, circuits and wiring
• Emergency power requirements
• Technology system provisions (conduit stubs, cable tray, etc.)
• Lighting
• Theatrical lighting and controls
• Electrical scoreboards
• Rough-in for security system
• Site Lighting
• Fire Alarm System

28A - Security, Sound & Technology Systems – Preliminary Estimate $2,008,678

• Communications & Telecom
• Clock system
• Paging/Central Sound
• Music room sound
• Gym & Stage sound system
• Student dining audio/video system
• Classroom audio/video system
• Electronic Safety & Security

32A - Final Site Development – Preliminary Estimate $586,177

• Asphalt Paving
• Repair stone base
• Striping
• Topsoil spreading
• Landscaping
• Irrigation System
• Flagpole
• Site furnishings
• Site signage
• Fencing Install
• Salvaged Statues
 
CM AT RISK