Amherst EVSD - PK-3 Elementary School

Amherst Exempted Village School District is building a new, 103,000 square foot Elementary School that will house 939 students in grades PK-3 and will be built in accordance with the Ohio School Design Manual.

  • Owner: Amherst Exempted Village School District
  • Co-Owner: Ohio Facilities Construction Commission
  • Architect: GPD Group
  • CM at Risk: ICON, LLC.
  • Location: Amherst, Ohio
  • Size: 103,000sf New PK-3 School
  • Value: $24 Million
  • Anticipated Bid Date: Demo - July 27, 2017; Early Site - December 1, 2017; New School - March 1, 2018
  • Construction: 

PREQUALIFICATION OF SUBCONTRACTORS
ICON, LLC will be prequalifying subcontractors with criteria that has been pre-approved by the OFCC and the AEVSD in accordance with the guidelines set forth by the State of Ohio for CMaR contracting. More information and documents related to this project delivery format can be found at http://ofcc.ohio.gov/Documents.aspx. Although ICON, LLC will share information on bids received with the Co-Owners, this is not a public bid opening. More information on bid delivery will be issued with the bid packages to pre-qualified subcontractors. Questions on the process should be sent to amherstbidquestions@iconohio.com.

Contractors wishing to be considered for pre-qualification must do so by providing information on the web-tool at the link below. Information will be treated as confidential, and only shared with the members of ICON, AEVSD and the OFCC involved with the pre-qualification process.

SUBCONTRACTOR BID PACKAGES
ICON will be receiving bids from prequalified subcontractors on the bid packages listed below. It is also ICON’s intent to allow for the bidding of Combination Bids. We believe that this practice will allow for additional competition in the market, sustain the viability of local general contractors and allow the inclusion of smaller subcontractors who might otherwise be ineligible. Scope indicated below are for general information, only. Detailed scopes of work will be issued with each bid package.

Hazardous Material Abatement

• Removal and disposal of all ACM's
• Removal and disposal of PCB & mercury containing material
• Misc. hazmat removals
• Universal waste disposal

Demolition and Site Restoration

• Establish and maintain site access and SWP-3
• Utility terminations
• Demolish and dispose of all structures
• Import soils, backfill, grade and topsoil placement
• Seed and maintain lawn until completion